A.4.1.1.25a - Pemasangan 1 M2 bekisting untuk dinding
| A.4.1.1.25a - Pemasangan 1 M2 bekisting untuk dinding | |||||
|---|---|---|---|---|---|
| NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
| A | TENAGA | ||||
| Pekerja | OH | 0,6600 | 81.500,00 | 53.790,00 | |
| Tukang Kayu | OH | 0,3300 | 96.500,00 | 31.845,00 | |
| Kepala Tukang | OH | 0,0330 | 107.000,00 | 3.531,00 | |
| Mandor | OH | 0,0330 | 107.000,00 | 3.531,00 | |
| JUMLAH HARGA TENAGA | 92.697,00 | ||||
| B | BAHAN | ||||
| Kayu kelas III | M' | 0,0300 | 3.500.000,00 | 105.000,00 | |
| Paku 5 cm – 12 cm | Kg | 0,4000 | 23.000,00 | 9.200,00 | |
| Minyak bekisting | Liter | 0,2000 | 5.150,00 | 1.030,00 | |
| Balok kayu kelas II | M' | 0,0200 | 4.500.000,00 | 90.000,00 | |
| Plywood tebal 9 mm | Lbr | 0,3500 | 125.000,00 | 43.750,00 | |
| Dolken Bambu | Batang | 3,0000 | 25.000,00 | 75.000,00 | |
| Penjaga jarak bekisting/ spacer | Buah | 4,0000 | 6.000,00 | 24.000,00 | |
| JUMLAH HARGA BAHAN | 347.980,00 | ||||
| C | ALAT | ||||
| - | - | - | - | - | |
| JUMLAH HARGA ALAT | - | ||||
| D | Jumlah | (A+B+C) | 440.677,00 | ||
| E | Overhead & Profit | 10% x D | 44.067,70 | ||
| F | HARGA SATUAN PEKERJAAN | ( D + E ) | 484.744,70 | ||