Skip to content Skip to sidebar Skip to footer

A.4.1.1.28 - Membuat 1 M3 pondasi beton bertulang (150 Kg besi + bekisting)

A.4.1.1.28 - Membuat 1 M3 pondasi beton bertulang (150 Kg besi +   bekisting)
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 5,3000 81.500,00 431.950,00
Tukang batu OH 0,2750 96.500,00 26.537,50
Tukang kayu OH 1,3000 96.500,00 125.450,00
Tukang besi OH 1,0500 96.500,00 101.325,00
Kepala tukang OH 0,2620 107.000,00 28.034,00
Mandor OH 0,2650 107.000,00 28.355,00
JUMLAH HARGA TENAGA 741.651,50
B BAHAN
Kayu kelas III M3 0,2000 3.500.000,00 700.000,00
Paku 5 cm – 12 cm Kg 1,5000 23.000,00 34.500,00
Minyak bekisting Liter 0,4000 5.150,00 2.060,00
Besi beton polos Kg 157,5000 10.100,00 1.590.750,00
Kawat beton Kg 2,2500 23.500,00 52.875,00
Semen Portland Kg 336,0000 1.250,00 420.000,00
Pasir Beton M3 0,5400 350.000,00 189.000,00
Kerikil M3 0,8100 364.000,00 294.840,00
JUMLAH HARGA BAHAN 3.284.025,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4.025.676,50
E Overhead & Profit 10% x D 402.567,65
F HARGA SATUAN   PEKERJAAN ( D + E ) 4.428.244,15



======= ARTIKEL TERKAIT =======



Post a Comment for "A.4.1.1.28 - Membuat 1 M3 pondasi beton bertulang (150 Kg besi + bekisting)"