A.4.2.1.21 - Pemasangan 1 M2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon
| A.4.2.1.21 - Pemasangan 1 M2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon | |||||
|---|---|---|---|---|---|
| NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
| A | TENAGA | ||||
| Pekerja | OH | 0,3500 | 81.500,00 | 28.525,000 | |
| Tukang Besi | OH | 0,3500 | 96.500,00 | 33.775,000 | |
| Kepala Tukang | OH | 0,0350 | 107.000,00 | 3.745,000 | |
| Mandor | OH | 0,0180 | 107.000,00 | 1.926,000 | |
| JUMLAH HARGA TENAGA | 67.971,000 | ||||
| B | BAHAN | ||||
| Rangka metal hollow 40.40 mm | M' | 4,0000 | 6.000,00 | 24.000,000 | |
| Assesoris (perkuatan, baut, las dll) | Ls | 100%xrangka | 21.000,00 | 21.000,000 | |
| JUMLAH HARGA BAHAN | 45.000,000 | ||||
| C | ALAT | ||||
| - | - | - | - | - | |
| JUMLAH HARGA ALAT | - | ||||
| D | Jumlah | (A+B+C) | 112.971,000 | ||
| E | Overhead & Profit | 10% x D | 11.297,10 | ||
| F | HARGA SATUAN PEKERJAAN | ( D + E ) | 124.268,10 | ||