A.4.2.1.5 - Pengerjaan 10 Cm pengelasan dengan las listrik
| A.4.2.1.5 - Pengerjaan 10 Cm pengelasan dengan las listrik |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,0400 |
81.500,00 |
3.260,00 |
| |
TukangKonstruksiBesi |
OH |
0,0200 |
96.500,00 |
1.930,00 |
| |
Kepala tukang |
OH |
0,0020 |
107.000,00 |
214,00 |
| |
Mandor |
OH |
0,0020 |
107.000,00 |
214,00 |
| |
|
|
JUMLAH HARGA TENAGA |
5.618,00 |
| B |
BAHAN |
|
|
|
|
| |
Kawat las listrik |
Kg |
0,4000 |
36.150,00 |
14.460,00 |
| |
Solar |
Liter |
0,3000 |
10.200,00 |
3.060,00 |
| |
Minyak pelumas |
Liter |
0,0400 |
55.000,00 |
2.200,00 |
| |
|
|
JUMLAH HARGA BAHAN |
19.720,00 |
| C |
ALAT |
|
|
|
|
| |
Sewa alat |
Jam |
0,1700 |
270.000,00 |
45.900,00 |
| |
|
|
JUMLAH HARGA ALAT |
45.900,00 |
| D |
Jumlah |
(A+B+C) |
|
|
71.238,00 |
| E |
Overhead & Profit |
10% x D |
|
|
7.123,80 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
78.361,80 |