A.4.4.2.20. Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10 cm
A.4.4.2.20. Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10 cm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,0800 |
81.500,00 |
6.520,00 |
|
Tukang Batu |
OH |
0,4000 |
96.500,00 |
38.600,00 |
|
Kepala Tukang |
OH |
0,0400 |
107.000,00 |
4.280,00 |
|
Mandor |
OH |
0,0040 |
107.000,00 |
428,00 |
|
|
|
JUMLAH HARGA TENAGA |
49.828,00 |
B |
BAHAN |
|
|
|
|
|
Portland Cement |
Kg |
0,5000 |
1.250,00 |
625,00 |
|
Pasir Pasang |
M3 |
0,0130 |
350.000,00 |
4.550,00 |
|
|
|
JUMLAH HARGA BAHAN |
5.175,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
55.003,00 |
E |
Overhead & Profit |
10% x D |
|
|
5.500,30 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
60.503,30 |