A.4.4.2.3 - Pemasangan 1 M2 plesteran 1SP : 3PP tebal 15mm
A.4.4.2.3 - Pemasangan 1 M2 plesteran 1SP : 3PP tebal 15mm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,3000 |
81.500,00 |
24.450,00 |
|
Tukang Batu |
OH |
0,1500 |
96.500,00 |
14.475,00 |
|
Kepala Tukang |
OH |
0,0150 |
107.000,00 |
1.605,00 |
|
Mandor |
OH |
0,0150 |
107.000,00 |
1.605,00 |
|
|
|
JUMLAH HARGA TENAGA |
42.135,00 |
B |
BAHAN |
|
|
|
|
|
Portland Cement |
Kg |
7,7760 |
1.250,00 |
9.720,00 |
|
Pasir Pasang |
M3 |
0,0230 |
350.000,00 |
8.050,00 |
|
|
|
JUMLAH HARGA BAHAN |
17.770,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
59.905,00 |
E |
Overhead & Profit |
10% x D |
|
|
5.990,50 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
65.895,50 |