Skip to content Skip to sidebar Skip to footer

A.4.4.3.54b - Pemasangan 1 M2 dinding keramik 25cm x 40cm

A.4.4.3.54b - Pemasangan 1 M2 dinding keramik   25cm x 40cm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,9000 81.500,00 73.350,00
Tukang Batu OH 0,4500 96.500,00 43.425,00
Kepala tukang OH 0,0450 107.000,00 4.815,00
Mandor OH 0,0450 107.000,00 4.815,00
JUMLAH HARGA TENAGA 126.405,00
B BAHAN
Keramik Bh 10,0000 6.000,00 60.000,00
Semen Portland Kg 9,3000 1.250,00 11.625,00
Pasir Pasang M3 0,0180 350.000,00 6.300,00
Semen warna Kg 1,9400 5.000,00 9.700,00
JUMLAH HARGA BAHAN 87.625,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 214.030,00
E Overhead & Profit 10% x D 21.403,00
F HARGA SATUAN   PEKERJAAN ( D + E )    235.433,00