A.4.4.3.9a - Pemasangan 1 M2 lantai ubin granit polished ukuran 30cm x 60cm
| A.4.4.3.9a - Pemasangan 1 M2 lantai ubin granit polished ukuran 30cm x 60cm |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,2500 |
81.500,00 |
20.375,00 |
| |
Tukang Batu |
OH |
0,1250 |
96.500,00 |
12.062,50 |
| |
Kepala tukang |
OH |
0,0130 |
107.000,00 |
1.391,00 |
| |
Mandor |
OH |
0,0130 |
107.000,00 |
1.391,00 |
| |
|
|
JUMLAH HARGA TENAGA |
35.219,50 |
| B |
BAHAN |
|
|
|
|
| |
Ubin granit polished |
Bh |
5,9360 |
44.064,75 |
261.568,35 |
| |
Semen Portland |
Kg |
9,8000 |
1.250,00 |
12.250,00 |
| |
Semen warna |
Kg |
1,3000 |
5.000,00 |
6.500,00 |
| |
Pasir pasang |
M3 |
0,0450 |
350.000,00 |
15.750,00 |
| |
|
|
JUMLAH HARGA BAHAN |
296.068,35 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
331.287,85 |
| E |
Overhead & Profit |
10% x D |
|
|
33.128,78 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
364.416,63 |