A.4.5.2.12a - Pemasangan 1 M2 atap asbes gelombang 300 cm X 108 cm X 5 mm

A.4.5.2.12a - Pemasangan 1 M2 atap asbes gelombang 300 cm X 108   cm X 5 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1400 81.500,00 11.410,00
Tukang Kayu OH 0,0700 96.500,00 6.755,00
Kepala tukang OH 0,0070 107.000,00 749,00
Mandor OH 0,0070 107.000,00 749,00
JUMLAH HARGA TENAGA 19.663,00
B BAHAN
Asbes gel 300 x 108 cm Lbr 0,3300 80.000,00 26.400,00
Paku pancing 6x23 Kg 0,1200 25.000,00 3.000,00
JUMLAH HARGA BAHAN 29.400,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 49.063,00
E Overhead & Profit 10% x D 4.906,30
F HARGA SATUAN   PEKERJAAN ( D + E )    53.969,30