A.4.5.2.38b - Pemasangan 1 M2 atap Zingcalum tebal 0.5 mm
A.4.5.2.38b - Pemasangan 1 M2 atap Zingcalum tebal 0.5 mm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,1200 |
81.500,00 |
9.780,00 |
|
Tukang Kayu |
OH |
0,0600 |
96.500,00 |
5.790,00 |
|
Kepala tukang |
OH |
0,0060 |
107.000,00 |
642,00 |
|
Mandor |
OH |
0,0060 |
107.000,00 |
642,00 |
|
|
|
JUMLAH HARGA TENAGA |
16.854,00 |
B |
BAHAN |
|
|
|
|
|
Zingcalum |
Lbr |
1,0500 |
55.000,00 |
57.750,00 |
|
Paku biasa ½”-1” |
Kg |
0,0200 |
23.600,00 |
472,00 |
|
|
|
JUMLAH HARGA BAHAN |
58.222,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
75.076,00 |
E |
Overhead & Profit |
10% x D |
|
|
7.507,60 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
82.583,60 |