A.4.6.1.22 - Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas II
A.4.6.1.22 - Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas II |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,1000 |
81.500,00 |
8.150,00 |
|
Tukang kayu |
OH |
0,2000 |
96.500,00 |
19.300,00 |
|
Kepala tukang |
OH |
0,0200 |
107.000,00 |
2.140,00 |
|
Mandor |
OH |
0,0050 |
107.000,00 |
535,00 |
|
|
|
JUMLAH HARGA TENAGA |
30.125,00 |
B |
BAHAN |
|
|
|
|
|
Papan kayu |
M3 |
0,0110 |
9.500.000,00 |
104.500,00 |
|
Paku 5 dan 7 cm |
Kg |
0,0500 |
23.000,00 |
1.150,00 |
|
|
|
JUMLAH HARGA BAHAN |
105.650,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
135.775,00 |
E |
Overhead & Profit |
10% x D |
|
|
13.577,50 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
149.352,50 |