A.4.6.1.26 - Pemasangan 1 M2 dinding lambrisering dari papan kayu kelas I
| A.4.6.1.26 - Pemasangan 1 M2 dinding lambrisering dari papan kayu kelas I |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,6000 |
81.500,00 |
48.900,00 |
| |
Tukang kayu |
OH |
1,8000 |
96.500,00 |
173.700,00 |
| |
Kepala tukang |
OH |
0,1800 |
107.000,00 |
19.260,00 |
| |
Mandor |
OH |
0,0300 |
107.000,00 |
3.210,00 |
| |
|
|
JUMLAH HARGA TENAGA |
245.070,00 |
| B |
BAHAN |
|
|
|
|
| |
Papan kayu |
M3 |
0,0070 |
29.200.000,00 |
204.400,00 |
| |
Paku 5 dan 10 |
Kg |
0,1000 |
23.000,00 |
2.300,00 |
| |
Paku skrup 10 cm |
Kg |
0,1500 |
75.000,00 |
11.250,00 |
| |
|
|
JUMLAH HARGA BAHAN |
217.950,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
463.020,00 |
| E |
Overhead & Profit |
10% x D |
|
|
46.302,00 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
509.322,00 |