Skip to content
A.4.7.1.16 - Pengecatan 1 M2 permukaan baja dengan menie besi
| A.4.7.1.16 - Pengecatan 1 M2 permukaan baja dengan menie besi |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,0200 |
81.500,00 |
1.630,00 |
| |
Tukang cat |
OH |
0,2000 |
96.500,00 |
19.300,00 |
| |
Kepala tukang |
OH |
0,0200 |
107.000,00 |
2.140,00 |
| |
Mandor |
OH |
0,0025 |
107.000,00 |
267,50 |
| |
|
|
JUMLAH HARGA TENAGA |
23.337,50 |
| B |
BAHAN |
|
|
|
|
| |
Menie besi |
Kg |
0,1000 |
25.000,00 |
2.500,00 |
| |
Kwas |
Bh |
0,0100 |
7.500,00 |
75,00 |
| |
|
|
JUMLAH HARGA BAHAN |
2.575,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
25.912,50 |
| E |
Overhead & Profit |
10% x D |
|
|
2.591,25 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
28.503,75 |