A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½”
| A.5.1.1.18 - Pemasangan 1 M' pipa galvanis diameter ½” | |||||
|---|---|---|---|---|---|
| NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
| A | TENAGA | ||||
| Pekerja | OH | 0,0540 | 81.500,00 | 4.401,00 | |
| Tukang batu | OH | 0,0900 | 96.500,00 | 8.685,00 | |
| Kepala tukang | OH | 0,0090 | 107.000,00 | 963,00 | |
| Mandor | OH | 0,0270 | 107.000,00 | 2.889,00 | |
| JUMLAH HARGA TENAGA | 16.938,00 | ||||
| B | BAHAN | ||||
| Pipa galvanis medium A ½” | M | 1,2000 | 23.000,00 | 27.600,00 | |
| Perlengkapan | Ls | 35%xpipa | 8.050,00 | 8.050,00 | |
| JUMLAH HARGA BAHAN | 35.650,00 | ||||
| C | ALAT | ||||
| - | - | - | - | - | |
| JUMLAH HARGA ALAT | - | ||||
| D | Jumlah | (A+B+C) | 52.588,00 | ||
| E | Overhead & Profit | 10% x D | 5.258,80 | ||
| F | HARGA SATUAN PEKERJAAN | ( D + E ) | 57.846,80 | ||