A.5.1.1.20 - Pemasangan 1 M' pipa galvanis diameter 3/4”
A.5.1.1.20 - Pemasangan 1 M' pipa galvanis diameter 3/4” |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,0540 |
81.500,00 |
4.401,00 |
|
Tukang batu |
OH |
0,0900 |
96.500,00 |
8.685,00 |
|
Kepala tukang |
OH |
0,0090 |
107.000,00 |
963,00 |
|
Mandor |
OH |
0,0270 |
107.000,00 |
2.889,00 |
|
|
|
JUMLAH HARGA TENAGA |
16.938,00 |
B |
BAHAN |
|
|
|
|
|
Pipa galvanis medium A 3/4” |
M |
1,2000 |
30.000,00 |
36.000,00 |
|
Perlengkapan |
% |
35,0000 |
10.500,00 |
10.500,00 |
|
|
|
JUMLAH HARGA BAHAN |
46.500,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
63.438,00 |
E |
Overhead & Profit |
10% x D |
|
|
6.343,80 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
69.781,80 |