NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0360 81.500,00 2.934,00
Tukang batu OH 0,0600 96.500,00 5.790,00
Kepala tukang OH 0,0060 107.000,00 642,00
Mandor OH 0,0020 107.000,00 214,00
JUMLAH HARGA TENAGA 9.580,00
B BAHAN
Pipa PVC 3/4” M 1,2000 7.500,00 9.000,00
Perlengkapan % 35,0000 2.625,00 2.625,00
JUMLAH HARGA BAHAN 11.625,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 21.205,00
E Overhead & Profit 10% x D 2.120,50
F HARGA SATUAN   PEKERJAAN ( D + E )    23.325,50