T.08.b.3 - 1 M3 Galian batu sedalam > 2 m s.d. 3 m
| T.08.b.3 - 1 M3 Galian batu sedalam > 2 m s.d. 3 m | |||||
|---|---|---|---|---|---|
| NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
| A | TENAGA | ||||
| 1 | Pekerja | OH | 1,3200 | 81.500,00 | 107.580,00 |
| 2 | Mandor | OH | 0,1320 | 115.000,00 | 15.180,00 |
| JUMLAH HARGA TENAGA | 122.760,00 | ||||
| B | BAHAN | ||||
| BBM non subsidi | Liter | 2,5000 | 9.850,00 | 24.625,00 | |
| JUMLAH HARGA BAHAN | 24.625,00 | ||||
| C | ALAT | ||||
| 1 | Jack hammer ** | Sewa-Hari | 0,2500 | 360.000,00 | 90.000,00 |
| JUMLAH HARGA ALAT | 90.000,00 | ||||
| D | Jumlah | (A+B+C) | 237.385,00 | ||
| E | Overhead & Profit | 10% x D | 23.738,50 | ||
| F | HARGA SATUAN PEKERJAAN | ( D + E ) | 261.123,50 | ||
| ** Jika dilaklukan tanpa menggunakan peralatan, maka harga satuan diberi nilai 0 | |||||