T.10.a.1 - 1 M3 Galian lumpur sedalam < 1 m
| T.10.a.1 - 1 M3 Galian lumpur sedalam < 1 m |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| 1 |
Pekerja |
OH |
0,8300 |
81.500,00 |
67.645,00 |
| 2 |
Mandor |
OH |
0,0830 |
115.000,00 |
9.545,00 |
| |
|
|
JUMLAH HARGA TENAGA |
77.190,00 |
| B |
BAHAN |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA BAHAN |
- |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
77.190,00 |
| E |
Overhead & Profit |
10% x D |
|
|
7.719,00 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
84.909,00 |