T.11.a.3 - 1 M3 Galian pasir untuk pondasi bangunan sedalam > 2 m s.d 3m’
| T.11.a.3 - 1 M3 Galian pasir untuk pondasi bangunan sedalam > 2 m s.d 3m’ |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| 1 |
Pekerja |
OH |
0,9200 |
81.500,00 |
74.980,00 |
| 2 |
Mandor |
OH |
0,0920 |
115.000,00 |
10.580,00 |
| |
|
|
JUMLAH HARGA TENAGA |
85.560,00 |
| B |
BAHAN |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA BAHAN |
- |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
85.560,00 |
| E |
Overhead & Profit |
10% x D |
|
|
8.556,00 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
94.116,00 |