A.4.2.1.10 - Pemasangan 1 M2 rolling door alluminium
| A.4.2.1.10 - Pemasangan 1 M2 rolling door alluminium |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
1,0000 |
81.500,00 |
81.500,00 |
| |
TukangAlumuniumKhusus |
OH |
1,0000 |
96.500,00 |
96.500,00 |
| |
Kepala tukang |
OH |
0,1000 |
107.000,00 |
10.700,00 |
| |
Mandor |
OH |
0,0500 |
107.000,00 |
5.350,00 |
| |
|
|
JUMLAH HARGA TENAGA |
194.050,00 |
| B |
BAHAN |
|
|
|
|
| |
Rolling dor alluminium |
M2 |
1,0000 |
475.000,00 |
475.000,00 |
| |
|
|
JUMLAH HARGA BAHAN |
475.000,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
669.050,00 |
| E |
Overhead & Profit |
10% x D |
|
|
66.905,00 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
735.955,00 |