Skip to content Skip to sidebar Skip to footer

A.4.2.1.11a - Pemasangan 1 M' kusen pintu alluminium Silver 3"

A.4.2.1.11a - Pemasangan 1 M' kusen pintu alluminium Silver   3"
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0430 81.500,00 3.504,50
TukangAlumuniumKhusus OH 0,0430 96.500,00 4.149,50
Kepala tukang OH 0,0043 107.000,00 460,10
Mandor OH 0,0021 107.000,00 224,70
JUMLAH HARGA TENAGA 8.338,80
B BAHAN
Profil alluminium silver 3" M' 1,1000 70.000,00 77.000,00
Skrup fixer Buah 2,0000 1.500,00 3.000,00
Sealant Tube 0,0600 12.500,00 750,00
JUMLAH HARGA BAHAN 80.750,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 89.088,80
E Overhead & Profit 10% x D 8.908,88
F HARGA SATUAN   PEKERJAAN ( D + E ) 97.997,68



======= ARTIKEL TERKAIT =======



Post a Comment for "A.4.2.1.11a - Pemasangan 1 M' kusen pintu alluminium Silver 3""