A.4.2.1.11f - Pemasangan 1 M' kusen pintu alluminium Coklat 4"
A.4.2.1.11f - Pemasangan 1 M' kusen pintu alluminium Coklat 4" |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,0430 |
81.500,00 |
3.504,50 |
|
TukangAlumuniumKhusus |
OH |
0,0430 |
96.500,00 |
4.149,50 |
|
Kepala tukang |
OH |
0,0043 |
107.000,00 |
460,10 |
|
Mandor |
OH |
0,0021 |
107.000,00 |
224,70 |
|
|
|
JUMLAH HARGA TENAGA |
8.338,80 |
B |
BAHAN |
|
|
|
|
|
Profil alluminium Coklat 4" |
M' |
1,1000 |
90.000,00 |
99.000,00 |
|
Skrup fixer |
Buah |
2,0000 |
1.500,00 |
3.000,00 |
|
Sealant |
Tube |
0,0600 |
12.500,00 |
750,00 |
|
|
|
JUMLAH HARGA BAHAN |
102.750,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
111.088,80 |
E |
Overhead & Profit |
10% x D |
|
|
11.108,88 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
122.197,68 |