A.4.2.1.15 - Pemasangan 1 M2 terali besi strip (2 x 3) mm
A.4.2.1.15 - Pemasangan 1 M2 terali besi strip (2 x 3) mm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,6700 |
81.500,00 |
136.105,00 |
|
Tukang Las |
OH |
1,6700 |
96.500,00 |
161.155,00 |
|
Kepala tukang |
OH |
0,1670 |
107.000,00 |
17.869,00 |
|
Mandor |
OH |
0,0830 |
107.000,00 |
8.881,00 |
|
|
|
JUMLAH HARGA TENAGA |
324.010,00 |
B |
BAHAN |
|
|
|
|
|
Besi strip |
Kg |
6,1770 |
15.200,00 |
93.890,40 |
|
Pengelasan |
Cm |
27,0800 |
7.836,18 |
212.203,75 |
|
|
|
JUMLAH HARGA BAHAN |
306.094,15 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
630.104,15 |
E |
Overhead & Profit |
10% x D |
|
|
63.010,42 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
693.114,57 |