Skip to content
A.4.2.1.2 - Pemasangan 1 Kg rangka kuda-kuda baja IWF
| A.4.2.1.2 - Pemasangan 1 Kg rangka kuda-kuda baja IWF |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,0600 |
81.500,00 |
4.890,00 |
| |
TukangKonstruksiLas |
OH |
0,0600 |
96.500,00 |
5.790,00 |
| |
Kepala tukang |
OH |
0,0060 |
107.000,00 |
642,00 |
| |
Mandor |
OH |
0,0030 |
107.000,00 |
321,00 |
| |
|
|
JUMLAH HARGA TENAGA |
11.643,00 |
| B |
BAHAN |
|
|
|
|
| |
Besi Baja IWF |
Kg |
1,1500 |
12.700,00 |
14.605,00 |
| |
|
|
JUMLAH HARGA BAHAN |
14.605,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
26.248,00 |
| E |
Overhead & Profit |
10% x D |
|
|
2.624,80 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
28.872,80 |
======= ARTIKEL TERKAIT =======
Post a Comment for "A.4.2.1.2 - Pemasangan 1 Kg rangka kuda-kuda baja IWF"