A.4.2.1.3 - Pengerjaan 100 Kg pekerjaan perakitan
| A.4.2.1.3 - Pengerjaan 100 Kg pekerjaan perakitan |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,1000 |
81.500,00 |
8.150,00 |
| |
TukangKonstruksiBesi |
OH |
0,1000 |
96.500,00 |
9.650,00 |
| |
Kepala tukang |
OH |
0,0010 |
107.000,00 |
107,00 |
| |
Mandor |
OH |
0,0050 |
107.000,00 |
535,00 |
| |
|
|
JUMLAH HARGA TENAGA |
18.442,00 |
| B |
BAHAN |
|
|
|
|
| |
Solar |
Liter |
1,0000 |
10.200,00 |
10.200,00 |
| |
Minyak pelumas |
Liter |
0,1000 |
55.000,00 |
5.500,00 |
| |
|
|
JUMLAH HARGA BAHAN |
15.700,00 |
| C |
ALAT |
|
|
|
|
| |
1. Sewa alat |
Jam |
0,8000 |
270.000,00 |
216.000,00 |
| |
|
|
JUMLAH HARGA ALAT |
216.000,00 |
| D |
Jumlah |
(A+B+C) |
|
|
250.142,00 |
| E |
Overhead & Profit |
10% x D |
|
|
25.014,20 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
275.156,20 |