A.4.5.2.24 - Pemasangan 1 M' bubung stel gelombang 1,08m
| A.4.5.2.24 - Pemasangan 1 M' bubung stel gelombang 1,08m |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,0840 |
81.500,00 |
6.846,00 |
| |
Tukang Kayu |
OH |
0,1250 |
96.500,00 |
12.062,50 |
| |
Kepala tukang |
OH |
0,0130 |
107.000,00 |
1.391,00 |
| |
Mandor |
OH |
0,0040 |
107.000,00 |
428,00 |
| |
|
|
JUMLAH HARGA TENAGA |
20.727,50 |
| B |
BAHAN |
|
|
|
|
| |
Bubung stel gel. |
Lbr |
2,0500 |
70.000,00 |
143.500,00 |
| |
Paku skrup 3,5” |
Bh |
6,0000 |
3.750,00 |
22.500,00 |
| |
|
|
JUMLAH HARGA BAHAN |
166.000,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
186.727,50 |
| E |
Overhead & Profit |
10% x D |
|
|
18.672,75 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
205.400,25 |