A.4.5.2.30 - Pemasangan 1 M2 genteng beton
A.4.5.2.30 - Pemasangan 1 M2 genteng beton |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,2000 |
81.500,00 |
16.300,00 |
|
Tukang Kayu |
OH |
0,1000 |
96.500,00 |
9.650,00 |
|
Kepala tukang |
OH |
0,0100 |
107.000,00 |
1.070,00 |
|
Mandor |
OH |
0,0100 |
107.000,00 |
1.070,00 |
|
|
|
JUMLAH HARGA TENAGA |
28.090,00 |
B |
BAHAN |
|
|
|
|
|
Genteng beton |
Bh |
11,0000 |
6.500,00 |
71.500,00 |
|
Paku biasa 2”-5” |
Kg |
0,0300 |
23.000,00 |
690,00 |
|
|
|
JUMLAH HARGA BAHAN |
72.190,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
100.280,00 |
E |
Overhead & Profit |
10% x D |
|
|
10.028,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
110.308,00 |