A.4.6.1.2 - Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela, kayu kelas II (kamfer)
| A.4.6.1.2 - Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela, kayu kelas II (kamfer) |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
6,0000 |
81.500,00 |
489.000,00 |
| |
Tukang kayu |
OH |
18,0000 |
96.500,00 |
1.737.000,00 |
| |
Kepala tukang |
OH |
1,8000 |
107.000,00 |
192.600,00 |
| |
Mandor |
OH |
0,3000 |
107.000,00 |
32.100,00 |
| |
|
|
JUMLAH HARGA TENAGA |
2.450.700,00 |
| B |
BAHAN |
|
|
|
|
| |
Balok kayu |
M3 |
1,2000 |
7.500.000,00 |
9.000.000,00 |
| |
Paku 10 cm |
Kg |
1,2500 |
23.000,00 |
28.750,00 |
| |
Lem kayu |
Kg |
1,0000 |
18.500,00 |
18.500,00 |
| |
|
|
JUMLAH HARGA BAHAN |
9.047.250,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
11.497.950,00 |
| E |
Overhead & Profit |
10% x D |
|
|
1.149.795,00 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
12.647.745,00 |