A.4.6.1.3 - Pembuatan dan pemasangan 1 M2 pintu klamp standar, kayu kelas II (kamper)
A.4.6.1.3 - Pembuatan dan pemasangan 1 M2 pintu klamp standar, kayu kelas II (kamper) |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,3500 |
81.500,00 |
28.525,00 |
|
Tukang kayu |
OH |
1,0500 |
96.500,00 |
101.325,00 |
|
Kepala tukang |
OH |
0,1050 |
107.000,00 |
11.235,00 |
|
Mandor |
OH |
0,0180 |
107.000,00 |
1.926,00 |
|
|
|
JUMLAH HARGA TENAGA |
143.011,00 |
B |
BAHAN |
|
|
|
|
|
Papan kayu |
M3 |
0,0400 |
9.500.000,00 |
380.000,00 |
|
Paku 5 – 7 cm |
Kg |
0,0500 |
23.000,00 |
1.150,00 |
|
|
|
JUMLAH HARGA BAHAN |
381.150,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
524.161,00 |
E |
Overhead & Profit |
10% x D |
|
|
52.416,10 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
576.577,10 |