A.4.6.1.5 - Pembuatan dan pemasangan 1 M2 daun pintu panel, kayu kelas II (kamfer)
A.4.6.1.5 - Pembuatan dan pemasangan 1 M2 daun pintu panel, kayu kelas II (kamfer) |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,0000 |
81.500,00 |
81.500,00 |
|
Tukang kayu |
OH |
3,0000 |
96.500,00 |
289.500,00 |
|
Kepala tukang |
OH |
0,3000 |
107.000,00 |
32.100,00 |
|
Mandor |
OH |
0,0500 |
107.000,00 |
5.350,00 |
|
|
|
JUMLAH HARGA TENAGA |
408.450,00 |
B |
BAHAN |
|
|
|
|
|
Papan kayu |
M3 |
0,0400 |
9.500.000,00 |
380.000,00 |
|
Lem kayu |
Kg |
0,5000 |
18.500,00 |
9.250,00 |
|
|
|
JUMLAH HARGA BAHAN |
389.250,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
797.700,00 |
E |
Overhead & Profit |
10% x D |
|
|
79.770,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
877.470,00 |