A.4.6.2.13.a - Pemasangan 1 Buah Gerendel
| A.4.6.2.13.a - Pemasangan 1 Buah Gerendel |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,0100 |
81.500,00 |
815,00 |
| |
Tukang kayu |
OH |
0,1000 |
96.500,00 |
9.650,00 |
| |
Kepala tukang |
OH |
0,0100 |
107.000,00 |
1.070,00 |
| |
Mandor |
OH |
0,0050 |
107.000,00 |
535,00 |
| |
|
|
JUMLAH HARGA TENAGA |
12.070,00 |
| B |
BAHAN |
|
|
|
|
| |
Gerendel |
Bh |
1,0000 |
10.000,00 |
10.000,00 |
| |
|
|
JUMLAH HARGA BAHAN |
10.000,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
22.070,00 |
| E |
Overhead & Profit |
10% x D |
|
|
2.207,00 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
24.277,00 |