Skip to content
A.4.6.2.14 - Pemasangan 1 Buah Rel pintu sorong
| A.4.6.2.14 - Pemasangan 1 Buah Rel pintu sorong |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| |
Pekerja |
OH |
0,0600 |
81.500,00 |
4.890,00 |
| |
Tukang kayu |
OH |
0,6000 |
96.500,00 |
57.900,00 |
| |
Kepala tukang |
OH |
0,0600 |
107.000,00 |
6.420,00 |
| |
Mandor |
OH |
0,0030 |
107.000,00 |
321,00 |
| |
|
|
JUMLAH HARGA TENAGA |
69.531,00 |
| B |
BAHAN |
|
|
|
|
| |
Rel pintu sorong |
Set |
1,0000 |
510.000,00 |
510.000,00 |
| |
|
|
JUMLAH HARGA BAHAN |
510.000,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
579.531,00 |
| E |
Overhead & Profit |
10% x D |
|
|
57.953,10 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
637.484,10 |