A.5.1.1.23 - Pemasangan 1 M' pipa galvanis diameter 3”
| A.5.1.1.23 - Pemasangan 1 M' pipa galvanis diameter 3” | |||||
|---|---|---|---|---|---|
| NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
| A | TENAGA | ||||
| Pekerja | OH | 0,1350 | 81.500,00 | 11.002,50 | |
| Tukang batu | OH | 0,2250 | 96.500,00 | 21.712,50 | |
| Kepala tukang | OH | 0,0230 | 107.000,00 | 2.461,00 | |
| Mandor | OH | 0,0070 | 107.000,00 | 749,00 | |
| JUMLAH HARGA TENAGA | 35.925,00 | ||||
| B | BAHAN | ||||
| Pipa galvanis medium A 3” | M | 1,2000 | 150.000,00 | 180.000,00 | |
| Perlengkapan | % | 35,0000 | 52.500,00 | 52.500,00 | |
| JUMLAH HARGA BAHAN | 232.500,00 | ||||
| C | ALAT | ||||
| - | - | - | - | - | |
| JUMLAH HARGA ALAT | - | ||||
| D | Jumlah | (A+B+C) | 268.425,00 | ||
| E | Overhead & Profit | 10% x D | 26.842,50 | ||
| F | HARGA SATUAN PEKERJAAN | ( D + E ) | 295.267,50 | ||