T.07.b.3 - 1 M3 Galian tanah berbatu sedalam > 2 m s.d. 3 m
T.07.b.3 - 1 M3 Galian tanah berbatu sedalam > 2 m s.d. 3 m |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
1 |
Pekerja |
OH |
0,5500 |
81.500,00 |
44.825,00 |
2 |
Mandor |
OH |
0,0550 |
115.000,00 |
6.325,00 |
|
|
|
JUMLAH HARGA TENAGA |
51.150,00 |
B |
BAHAN |
|
|
|
|
|
BBM non subsidi |
Liter |
1,2500 |
9.850,00 |
12.312,50 |
|
|
|
JUMLAH HARGA BAHAN |
12.312,50 |
C |
ALAT |
|
|
|
|
1 |
Jack hammer *** |
Sewa-Hari |
0,1250 |
360.000,00 |
45.000,00 |
|
|
|
JUMLAH HARGA ALAT |
45.000,00 |
D |
Jumlah |
(A+B+C) |
|
|
108.462,50 |
E |
Overhead & Profit |
10% x D |
|
|
10.846,25 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
119.308,75 |
** Jika dilaklukan tanpa menggunakan peralatan, maka harga satuan diberi nilai 0 |