Safelik Convert by Netralid
Done
T.08.b.1 - 1 M3 Galian batu sedalam < 1 m
T.08.b.1 - 1 M3 Galian batu sedalam < 1 m |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
1 |
Pekerja |
OH |
1,0000 |
81.500,00 |
81.500,00 |
2 |
Mandor |
OH |
0,1000 |
115.000,00 |
11.500,00 |
|
|
|
JUMLAH HARGA TENAGA |
93.000,00 |
B |
BAHAN |
|
|
|
|
|
BBM non subsidi |
Liter |
2,5000 |
9.850,00 |
24.625,00 |
|
|
|
JUMLAH HARGA BAHAN |
24.625,00 |
C |
ALAT |
|
|
|
|
1 |
Jack hammer ** |
Sewa-Hari |
0,2500 |
360.000,00 |
90.000,00 |
|
|
|
JUMLAH HARGA ALAT |
90.000,00 |
D |
Jumlah |
(A+B+C) |
|
|
207.625,00 |
E |
Overhead & Profit |
10% x D |
|
|
20.762,50 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
228.387,50 |
** Jika dilaklukan tanpa menggunakan peralatan, maka harga satuan diberi nilai 0 |
======= ARTIKEL TERKAIT =======
Post a Comment for "T.08.b.1 - 1 M3 Galian batu sedalam < 1 m"