Skip to content
T.14.a.3 - 1 M3 Timbunan tanah Padas
| T.14.a.3 - 1 M3 Timbunan tanah Padas |
| NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
| A |
TENAGA |
|
|
|
|
| 1 |
Pekerja |
OH |
0,3300 |
81.500,00 |
26.895,00 |
| 2 |
Mandor |
OH |
0,0330 |
115.000,00 |
3.795,00 |
| |
|
|
JUMLAH HARGA TENAGA |
30.690,00 |
| B |
BAHAN |
|
|
|
|
| 1 |
Tanah Padas |
M3 |
1,2000 |
147.000,00 |
176.400,00 |
| |
|
|
JUMLAH HARGA BAHAN |
176.400,00 |
| C |
ALAT |
|
|
|
|
| |
- |
- |
- |
- |
- |
| |
|
|
JUMLAH HARGA ALAT |
- |
| D |
Jumlah |
(A+B+C) |
|
|
207.090,00 |
| E |
Overhead & Profit |
10% x D |
|
|
20.709,00 |
| F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
227.799,00 |
======= ARTIKEL TERKAIT =======
Post a Comment for "T.14.a.3 - 1 M3 Timbunan tanah Padas"