T.14.b.1 - 1 M3 Pemadatan tanah
T.14.b.1 - 1 M3 Pemadatan tanah |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
1 |
Pekerja |
OH |
0,5000 |
81.500,00 |
40.750,00 |
2 |
Mandor |
OH |
0,0500 |
115.000,00 |
5.750,00 |
|
|
|
JUMLAH HARGA TENAGA |
46.500,00 |
B |
BAHAN |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA BAHAN |
- |
C |
ALAT |
|
|
|
|
1 |
Pemadat Timbunan (Stamper) |
Sewa-Hari |
0,0500 |
381.237,44 |
19.061,87 |
|
|
|
JUMLAH HARGA ALAT |
19.061,87 |
D |
Jumlah |
(A+B+C) |
|
|
65.561,87 |
E |
Overhead & Profit |
10% x D |
|
|
6.556,19 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
72.118,06 |